Full scale demonstration of energy positive sewage treatment plant concepts towards market penetration

From 2015-07-01 to 2018-07-01, ongoing project

Project details

Total cost:

EUR 5 173 854,75

EU contribution:

EUR 3 997 125,99

Coordinated in:

Germany

Call for proposal:

H2020-WATER-2014-two-stage

Funding scheme:

IA - Innovation action

Objective

The municipal wastewater in Europe contains a potential chemical energy of 87,500 GWh per year in its organic fraction, which is equivalent to the output of 12 large power stations. Due to the currently applied technologies and related energy loss at each process step, wastewater treatment in Europe today consumes instead the equivalent of more than 2 power stations. Many operators are thus targeting incremental energy efficiency towards energy neutrality, but recent studies have shown that wi…
Expand / Contract(+)

Coordinator

KOMPENTENTZZENTRUM WASSER BERLIN GEMEINNUTZIGE GMBH
Germany

Participants

TECHNISCHE UNIVERSITAET WIEN
Austria
EIDGENOESSISCHE ANSTALT FUER WASSERVERSORGUNG ABWASSERREINIGUNG UND GEWAESSERSCHUTZ
Switzerland
FRAUNHOFER GESELLSCHAFT ZUR FORDERUNG DER ANGEWANDTEN FORSCHUNG EV
Germany
VEOLIA DEUTSCHLAND GMBH
Germany
VEOLIA WATER TECHNOLOGIES AB
Sweden
NEAS ENERGY AS
Denmark
BIOFOS AS
Denmark
Berliner Wasserbetriebe
Germany
UMWELTBUNDESAMT
Germany
ELECTROCHAEA DK APS
Denmark
APS AQUA PLANT SOLUTIONS GMBH
Germany
SUSTEC CONSULTING & CONTRACTING BV
Netherlands
Atemis GmbH ingenieurburo fur abwassertechnik energiemanagement und innovative systementwicklung
Germany
ARCTIK SPRL
Belgium